E46 series BMW 3

since 1998 of release

Repair and car operation



E46 series BMW 3
+ BMW 3 Cars (E46)
+ Current leaving and service
+ Engine
+ Systems of cooling, heating
+ Power supply systems, injection and release
- Engine electric equipment
   General information and security measures
   + System of electronic control by ignition and injection of the petrol engine
   + ignition System
   + System of preheat of the diesel engine
   - Charge and start systems
      General information on system
      The battery - the main data and leaving
      Removal and installation of the storage battery
      Check of the storage battery
      Generator. General information and security measures
      Removal and generator installation
      Check and replacement of brushes of a generator / regulator of tension
      Removal and installation, starter check
      Removal, installation and check of the traction relay of a starter
+ RKPP and transmission line
+ Automatic transmission
+ Coupling and power shafts
+ Brake system
+ Suspension bracket and steering
+ Body
+ Onboard electric equipment
+ electric equipment Schemes


2b332cca На divan-na-kuhniu.ru недорого купить диван на кухню.

Removal and installation, starter check

Starter elements

1 — a starter
2 — the electromagnetic actuator
3 — a gear wheel with the obgonny coupling
4 — the gear wheel lever

5 — a rotor
6
7 — the holder of brushes
8 — plugs


Starter check

To check a starter at full tension of the battery, it is necessary to connect plugs "30" (the big plug) and “50” (the small plug near big) a cable to cross-section section at least 4.0 mm2. If now the starter works faultlessly, it is necessary to check wires to a starter. If the starter does not turn, it should be removed and checked.

Exact check is carried out at the verifying stand or an electrotechnical workshop.

Removal and starter installation

The starter settles down sideways at a joint of the block of cylinders with RKPP and acts in film down.

 REMOVAL

1 Disconnect a negative cable (-) the storage battery at the switched-off ignition. The battery is in a luggage compartment behind a cover on the right side. At BMW 316i, 318i cars the battery settles down in an impellent compartment.

As a result of shutdown of the storage battery data from memory of malfunctions of some monitors are erased. If necessary before shutdown of the battery it is necessary to consider these memories of malfunctions. Address to the Section Diagnostics of malfunctions. Work it is desirable to lead HUNDRED in conditions.

2 Close negative полюсбатареи to exclude possibility of casual contact.

Lifting and car installation on supports are dangerous! Therefore previously familiarize with Poddomkrachivaniye's Section and towage

3 Lift and establish the car on supports. Remove the bottom cover of an impellent compartment, address to the Section Removal and installation of the bottom cover of an impellent compartment.
4 Models 320d: Remove a noise isolation on the left side of the engine, under a starter for what unscrew one bolt.
5 Models 316i, 318i, 320i, 323i, 328i: For improvement of access to the generator disconnect fuel hoses around a starter in places of their muftovy connections.

Observe given below a security measure. Separation of fuel hoses is described in the Section Removal and installation of injectors.

- Near a workplace do not smoke, do not use open fire and heated or very hot subjects. There is a danger of emergence of a fire! Keep in readiness the fire extinguisher.
- Watch surely good ventilation of a workplace. Fuel pairs are poisonous.
- The fuel system is under pressure. When opening system there can be a fuel emission. Wipe fuel a rag. Carry goggles.


6 Disconnect wires:

1–the plug 30, a thick wire directly from a positive pole of the storage battery;
2–the plug 50, from the ignition switch.

Mark wires that at assembly to attach them on former places.

7 Turn out bolts of fastening of a starter from a manual check point by means of the corresponding extension piece.
8 Take out a starter back from a flange of a check point and remove it down.

9 Check a gear wheel of a starter and a gear wreath on existence of damages.


 INSTALLATION

10 Establish into place a starter and fix it the moment of 50 N • m.
11 Join electric wires and fix them on the plug 30 the moment of 12 N • m, and on the plug 50 the moment of 6 N • m.

Lay wires just as before removal. Watch that. That they did not rub about adjacent designs.

12 Models 316i, 318i, 320i, 323i, 328i: Connect fuel hoses and fix and in the holder. Fastening execute by means of new collars. Sealing rings apply also new, address to the Section Removal and installation of injectors.
13 Models 320d: Insert a noise isolation under a starter and fix it.
14 Establish the bottom cover of an impellent compartment, address to the Section Removal and installation of the bottom cover of an impellent compartment.
15 Attach a negative cable (-) the storage battery at the switched-off ignition. Establish hours.